A risk assessment and method statement (RAMS) helps everyone involved in an activity understand the risks, the precautions that must be taken and how the work should be carried out safely.
To make preparing RAMS easier, our health and safety professionals have developed a free risk assessment and method statement template that you can download and adapt for your organisation.
The template provides a clear structure for recording hazards and control measures alongside the safe method of work. It also includes sample information to show how each section can be completed.
Download our free risk assessment and method statement template.
What is a risk assessment and method statement?
A risk assessment identifies the hazards associated with an activity, who could be harmed and the measures needed to control the risks. A method statement then explains how the work will be carried out safely, including the sequence of work and the controls that need to be followed.
Together, they are often referred to as RAMS (risk assessments and method statements) and help ensure everyone involved understands the risks and the safe way to complete the work.
A risk assessment and method statement template provides a consistent framework for recording this information. However, every assessment and method statement must reflect the specific activity, workplace, equipment, people involved and risks.
For more information, see our guide to what RAMS documents are and when they are used.
What is included in our free risk assessment and method statement template?
Our free method statement and risk assessment template includes sections for:
- Project and activity details – Record key information such as the work being carried out, location, dates and people responsible.
- Competency, training, permits and authorisations – Identify any specific competencies, training or permissions required before work begins.
- PPE, tools, equipment and materials – Specify what is needed to carry out the activity safely and effectively.
- Hazard identification and controls – Record the hazards, who could be harmed and the measures already in place to control the risks.
- Initial and residual risk ratings – Assess the level of risk before and after control measures are applied.
- Further actions – Record additional controls required, who is responsible for implementing them and target completion dates.
- 5 × 5 risk rating matrix – Use likelihood and severity scores to assess and prioritise risks consistently.
- Step-by-step method statement – Describe how the work will be carried out safely, including the sequence of tasks and controls required at each stage.
- Emergency arrangements – Document the procedures to follow if an incident, fire, spill or other emergency occurs.
- Environmental considerations – Identify potential environmental impacts and the measures needed to prevent or minimise harm.
- Monitoring, review and change control – Record how the RAMS will be monitored and when it should be reviewed or updated.
- Approval and operative acknowledgement – Confirm that the RAMS has been authorised and that those carrying out the work have read and understood it.
Sample information is included to show how the risk assessment method statement template can be completed. The examples are for guidance only and should be replaced with information specific to the activity, workplace, equipment, people involved and risks.
How to complete a risk assessment and method statement template
Completing RAMS requires careful consideration of how the work will be carried out and the associated risks. The document needs to reflect the activity, and the risks people could realistically encounter.
1. Describe the work
Start by clearly defining the activity. Record where and when the work will take place, who is responsible for it and the scope of the task.
Consider the people involved, equipment and materials being used, working environment and any other activities taking place nearby.
2. Identify the hazards
Consider what could cause harm at each stage of the work.
Depending on the activity, hazards could include vehicles, machinery, electricity, hazardous substances, manual handling, work at height, slips and trips, noise or interaction with members of the public.
Avoid relying on generic lists. The hazards recorded should be relevant to the real task and working environment.
3. Identify who could be harmed
Consider everyone who could be affected by the work, not only the employees carrying it out.
This could include contractors, visitors, customers, members of the public or other people working nearby. Some individuals may also be particularly vulnerable and require additional controls.
4. Record existing control measures
For each hazard, record the measures already in place to prevent harm or reduce the risk.
Controls might include safe systems of work, guarding, segregation, training, supervision, permits, inspection arrangements or personal protective equipment (PPE).
Controls should be specific enough for someone carrying out the activity to understand what is expected.
5. Assess the risk
Use your organisation’s approved risk-rating method to assess the level of risk.
Our method statement and risk assessment template includes an example 5 × 5 matrix based on likelihood and consequence. This helps determine which risks require further action and provides a consistent way to record initial and residual risk.
The matrix is provided as an example, so organisations with an existing risk-rating system should use their own approved methodology.
6. Identify further controls
Where the existing controls do not reduce the risk sufficiently, identify what else needs to be done.
Consider whether the hazard can be eliminated entirely before relying on measures that require people to follow procedures or wear PPE.
Record any additional actions clearly, including who is responsible for completing them and when they need to be completed.
7. Write the method statement
Once the risks and controls have been established, describe how the work will be completed safely.
Break the activity into a logical sequence and explain what needs to happen at each stage. Include relevant equipment, controls, checks, permits or hold points where necessary.
The method statement should reflect the findings of the risk assessment. A control identified in the assessment needs to be incorporated into the working method where relevant, rather than simply recorded in a table.
For more guidance, see our article explaining the purpose of a method statement.
8. Brief everyone involved
RAMS are only effective when the people carrying out the work understand them.
Employees and contractors should be briefed on the hazards, control measures and working method before starting the activity. They should also have an opportunity to ask questions or raise concerns.
Our template includes an operative acknowledgement section to record who has received and understood the RAMS.
9. Monitor and review
RAMS should reflect the conditions in which the work is taking place.
Review the document if circumstances change, new hazards are identified, an incident or near miss occurs, or there is reason to believe the existing controls are no longer effective.
Significant changes may require the work to stop while the risks are reassessed, and the method statement is updated.
Why use our risk assessment and method statement template?
A well-designed risk assessments and method statements template helps ensure important information is considered, including the hazards, risks, control measures and safe sequence of work.
However, the template itself does not make an activity safe. The quality of the RAMS depends on the information entered, the controls selected and how effectively they are implemented and shared.
Copying information from a previous assessment without considering the current activity can result in hazards being overlooked or controls being included that are not relevant. Each RAMS should be specific to the work being undertaken and reviewed whenever circumstances change.
To strengthen your RAMS and ensure they are fit for purpose, we offer a professional RAMS review service. Our health and safety consultants identify gaps, evaluate the controls and recommend improvements, helping you produce robust RAMS that protect those carrying out the work and support compliance.
Who can use our RAMS template?
Our risk assessment and method statement template can be adapted for a wide range of workplaces and activities.
It may be particularly useful for organisations managing maintenance, construction, engineering, facilities management, installation, repair or other activities where a clear method of work needs to be communicated alongside the risks and controls.
The level of detail should always be proportionate to the activity and the risks involved.
Download our free risk assessment and method statement template
Our free RAMS template provides a practical framework for assessing risks and setting out how work will be carried out safely.
Guidance and sample information are included to help you complete each section, covering hazards, control measures, the method of work, emergency arrangements, review and approval.

Adam Clarke
Managing Director (Consulting)